The critical path is the chain of tasks whose durations or dates can't slip without pushing your project's end date. MindGenius calculates it for you.

The critical path application calculates the path through your tasks whose durations or dates cannot be increased without having a negative impact on the eventual end date of your project.

Seeing it in action

The simplest way to see this is to add a few tasks to a project without linking any of them, then give one task a 2-day duration and the rest 1 day. Show the critical path and the 2-day task shows as critical, because it's the one controlling the end date of your project.

It stays live: in working out the critical route, MindGenius takes account of any links and constraints set against your tasks, and it's constantly re-evaluated, so any change to your schedule can change the critical path.

Most projects have a single critical path, but you can have more than one depending on how the schedule works out. Where that happens, MindGenius shows you each critical path that exists.